Construction preparation of new motorways towards Austria, Poland and Olomouc is in full swing

Construction preparation of new motorways towards Austria, Poland and Olomouc is in full swing
31/5/2017Press releases

The D11 motorway between Hradec Králové and Jaroměř and D35 in the sections Časy – Ostrov and Opatovice nad Labem – Časy are those that are in the most advanced preparation phase: construction should begin already in the autumn of this year. The government today received information on the preparation of all nine priority projects. These are projects for which the government has negotiated an exemption from a completely new environmental impact assessment, the so-called EIA.

Construction preparation of new motorways towards Austria, Poland and Olomouc is in full swing
"Archaeological research is currently under way on the D11 and D35 motorway sections and is an integral part of the construction process. Building machines can already be seen on the site. We want to start the actual construction by the end of this year, "says Transport Minister Dan Ťok. The archaeological survey is being performed on other priority projects as well, such as the D1 in the Říkovice – Přerov section, the D3 in section Úsilné – Hodějovice and Hodějovice – Třebonín and the D11 in section Smiřice – Jaroměř.

Other priority projects are the D6 in sections Lubenec – Nové Strašecí bypass – Řevničov and Řevničov – bypass, D48 – Frýdek-Místek bypass, D49 in section Hulín – Fryšták, D55 Otrokovice – south-east bypass and modernisation of the railway line between Sudoměřice and Votice.

The preparation of some projects is challenged by property settlements such as a lawsuit between the State Land Office and the Church due to the D11 route between Smiřice and Jaroměř involving the release of the land in question or a dispute with the landowners about the purchase price within the expropriation process under the route of the D55 motorway in the south-eastern by-pass of Otrokovice. For most priority projects, the building permit application has already been submitted or it will be submitted very soon.

You can find the current status of the individual building projects in the table below (click on the project name to open a page with more detailed information about the construction project):
 

Name of project

State of preparation

Submission of Building Permit Application

Expected construction

D3 0310/I Úsilné – Hodějovice

 

Property settlement is under way – expropriation processes, archaeological research started in 04/2017; the first tender round for general contractor is being evaluated (2nd round expected to start in 08/2017)

 

building permit applications submitted for the entire main route, two permits issued out of nine

Q4/2017

D3 0310/II Hodějovice – Třebonín

 

Property settlement is under way (expropriation), archaeological research started in 04/2017; the first tender round for general contractor is being evaluated (2nd round expected to start in 08/2017)

 

building permit applications submitted for the entire main route in accordance with act No. 416/2009 Coll.

Q4/2017

D6 Lubenec bypass

 

All land purchased on the main route, a long-term dispute with Lubenské strojírny s.r.o. settled; the Office for Protection of Competition (ÚOHS) rejected the remedy – 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017) 

the building permit application for the entire main route is in preparation

Q4/2017

D6 Nové Strašecí – Řevničov

 

Property settlement is under way – expropriation processes + settlement of land exchange – 100% of land on the main route has been handled and is ready for building permit issuance;the Office for Protection of Competition (ÚOHS) rejected the remedy – 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017) 

the building permit application for the entire main route is in preparation

Q4/2017

D6 Řevničov bypass

 

Property settlement is under way – expropriation processes; remedy filed with the Office for Protection of Competition (ÚOHS) – this obstructs the evaluation of the 1st tender round and start of the 2nd round (expected beginning of 2nd round in 06/2017) 

the building permit application for the entire main route is in preparation

Q4/2017

D11 1106 Hradec Králové – Smiřice

 

archaeological research has started, 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)

before building permit issuance  

Q3/2017

D11 1107 Smiřice – Jaroměř

 

Property settlement is under way – a church restitution dispute (the church refuses to give consent with the construction); archaeological research started; 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)

building permit applications have been filed

Q4/2017

D35 Časy – Ostrov

 

Property settlement is under way – expropriation processes, archaeological research has been started; the first tender round for general contractor is being evaluated (2nd round expected to start by the beginning of 06/2017)

building permit application was filed for the entire main route

Q3/2017

D35 Opatovice nad Labem – Časy

 

Property settlement is under way – expropriation processes, archaeological research has been started; the first tender round for general contractor is being evaluated (2nd round expected to start by the beginning of 06/2017)

building permit application was filed for the entire main route

Q3/2017

D48 Frýdek Místek – bypass

 

building proceedings in progress, 100% of the land has been purchased, 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)

building proceedings are under way

Q4/2017

D49 4901 Hulín – Fryšták

 

general contractor was selected

Building proceedings – legally effective exemption No.3 was granted for protected animals, a preliminary order was issued by the court for exemption No. 2 (hamster) (legally ineffective exemption)

Q4/2017

D55 5505 Otrokovice – south-east bypass

 

Property settlement in under way – there is an issue with the expropriation of husband and wife Gregůrkovy who submitted an expert opinion for a price over 2000 CZK/sqm. The expert opinion is incorrect; the usual price is one-tenth of that amount. ŘSD ČR disagrees with this expert opinion, the Expropriation Authority ordered an opinion review)

1st round of the tender for the general contractor was evaluated (2nd round expected to start in 08/2017)

The building permit application had been filed for the entire main route was withdrawn – an exemption from protected animals must be granted – application submitted with KÚ

Q4/2017

D1 0136 Říkovice – Přerov

 

Property settlement is under way – expropriation processes, a zoning permit amendment application was filed (04/2017; the exemption from protected animals was attacked, evaluation of the 1st tender round for general contractor is under way (2nd round expected to start in 11/2017)

the building permit application for the entire route in accordance with act No. 416/2009 Coll. is being prepared (it will be formally filed after the zoning permit amendment in about 07/2017); 

Q1/2018

Modernisation of the railway line between Sudoměřice and Votice

The civil design is under development

08/2017

Q3/2017






 
Back to article list